16th Street Early April Update
Phase 2 of the 16th Street Corridor Enhancement Project is now 85% complete! Work is progressing well, with crews focused on the remaining vertical elements, plantings, and irrigation. 16th Street remains open in both directions.
⚠ Upcoming Lane Closures — Please Plan Ahead
Temporary lane closures are coming to 16th Street over the next two weeks:
Next Week — Permanent Striping Installation
- Eastbound lanes closed: Monday & Tuesday
- Westbound lanes closed: Wednesday & Thursday
The Following Week — Light Pole Installation
- One-day closures in each direction (specific dates to be announced)
We appreciate your patience during these brief closures as we put the finishing touches on this project!
What's Been Completed
- 16th Street open in both directions
- Paver installation
- Bus shelter installation
- Sculpture foundations
- Trash receptacles
- Asphalt patching
- Topsoil and ground cover installation throughout the corridor
Work Currently Underway
- Seat wall and masonry wall construction
- Signage installation
- Plantings and irrigation
Coming Up Next
- Permanent striping (next week)
- Light pole installation (week of [DATE])
- Sculpture installation
16th Street Alley — Now Complete!
The 16th Street Alley is fully open. Improvements include new concrete pavement, a culvert over Ditch #3, fencing, and a repaved south parking lot — adding convenient parking for residents and businesses along the corridor.
Project Status at a Glance
Phase 2 Progress |
~85% complete |
Budget |
Within authorized funding |
16th Street |
Open in both directions |
9th & 10th Avenues |
Open |
Note: Some Phase 1 landscaping, lighting, and art installations will be completed during Phase 2 as weather allows.